Quang Binh Plant for sorting, disposing waste, producing biogas & organic mineral fertilizer
Quang Binh province,
Vietnam
- The pant was designed and built with the purpose of sorting, disposing waste, producing biogas & organic mineral fertilizer.
- Its nominal capacity is 300 tons/day for the waste classification; 1MW of biogas and electricity; and 5,000 tons/ year of the organic mineral fertilizers.
- Construction status: in progress
Location
Main Application
Industrial Structures
Project participants
Main Contractor: VINACONEX E&C – INPUT Ingenieure GmbH
Field Service
PERI Asia Pte Ltd. (Vietnam Rep. Office)
The Project
Impressions from the project process
This is the largest foreign invested project in Quang Binh with the 32mil EUR investment
Quang Binh Biogas Plant
Engineers of Vinaconex E&C with Experts and Consultants from Germany
Efficient and cost-effective concept with VARIO GT24 wall formwork for the casting height up to 8m per time
the VARIO GT 24 panel was being moved to installing position by crane
PERI Wall-formwork system ensured the dimensional accuracy of the finished concrete
multi-using times of VARIO GT 24 formwork system
Finished concrete surface
This is the largest foreign invested project in Quang Binh with the 32mil EUR investment
Quang Binh Biogas Plant
Engineers of Vinaconex E&C with Experts and Consultants from Germany
Efficient and cost-effective concept with VARIO GT24 wall formwork for the casting height up to 8m per time
the VARIO GT 24 panel was being moved to installing position by crane
PERI Wall-formwork system ensured the dimensional accuracy of the finished concrete
multi-using times of VARIO GT 24 formwork system
Finished concrete surface
Mr. Nguyen Xuan Tung
Site Manager
PERI products are very good, and the support for designing and solving incurred problems was very fast and well-cooperated. Though it was really a difficult challenge to assure the quality of the finished concrete surface with the up to 8 m wall-height at one time, but we still achieved a good result, and satisfied the Investors and Consultants of the project thanks to the stability of PERI formwork system.